Spotlight: KGE Logistics Deliver Vestas Windmill Parts To Belarus From All Over Europe

  29. April 2021
Spotlight: KGE Logistics Deliver Vestas Windmill Parts To Belarus From All Over Europe

In January 2021 our Latvian member, KGE logistics, was invited to complete a part delivery of the Vestas Windmill Project from Denmark, the Netherlands, and Latvia to the Asmolovichi Jobsite in Belarus. Due to a short delivery time, it was critical for the KGE team to make all arrangements in a short period.

The first part of the delivery was from Denmark and the Netherlands which required a multimodal solution to be adopted to deliver the below cargo to the consignee based in Asmolovich consecutively:

  • Lifting Tools on a 40” Flatbed trailer
  • Blade Gripper on a Lowbed
  • Barbeque Stand on a Curtain trailer
  • A 40” container consisting of various spare parts.

The second part of the shipment consisted of six windmill tower sections which were sent by their client to Ventspils harbor in Latvia from Spain using a breakbulk vessel. After the vessel arrived, the KGE team took care of all the port arrangements which included the dismantling of harbor gates to safely pass through, transit formalities, survey, and drone filming amongst others.

The Six tower sections had the following weights and dimensions:

Section

Weight (Kilograms)

Measurement (Meters)

Top

58000

32.35 x 3.258 x 3.67

Mid-Section 1

81000

18.2 x 4.979 x 4.989

Mid-Section 2

78000

21.840 x 4.182 x 4.979

Mid-Section 3

82500

26.880 x 3.927 x 4.182

Mid-Section 4

68000

28 x 3.671x 3.927

Bottom Section

82000

12.325 x 4.389x 5.30

In the end, all the shipments were delivered by the KGE team safely and well on time. The part delivery was concluded with any incidents.